Below is planned road work activity with potential to delay traffic on Inroads managed networks 28 April – 2 May (weather dependant)
NZTA STATE HIGHWAYS:
SH2, Arden Cottage Curve Realignment:
(adjacent to Athenree Rd intersection)
Anticipated completion: May 2014
Speed restriction through the site
Delays likely
SH 2, Te Puna Stream Bridge:
Water main replacement
Speed restrictions in place
Periodic Stop/Go between 9am and 4pm
Delays unlikely
SH 2, Te Puke: Kaituna Bridge:
Bridge repair work
30k/hr speed restriction through the site
Delays possible
Anticipated Completion: Late May
SH 29, Ruahihi to Soldiers Road:
Shoulder widening, sealing and wire rope barrier installation.
Shoulder closures with Contra Flow
Speed restrictions as required
Minor delays possible
Anticipated completion: early May
SH 29, Ngamuwahine Road 1 km length:
Seal widening, rehabilitation and wire rope barrier installation
30k/hr speed restrictions
Stop/Go as required
Delays likely
Anticipated completion: early May
SH36, between Taumata Road and Mangatoi Rd:
1km length of Seal Widening
Stop/Go traffic control
50k/hr speed restrictions
Minimal Delays
Anticipated completion: Mid May
WBOPDC LOCAL ROADS:
Nothing this week.