Construction of the Takitimu North Link has reached a major milestone, with all 10 bridges on stage one of the project now complete.
NZ Transport Agency Waka Kotahi (NZTA) says the achievement signals a major shift in the project, with construction moving from large-scale earthworks into road building and finishing works.
Together, the bridges span more than 1.5km of the 6.8km transport corridor, crossing waterways, gullies and the Kōpūrererua Valley.
A project update from NZTA said crews installed 279 piles and 198 bridge beams across the structures, with the deepest pile extending 67m underground and 43 bridge spans completed.
The milestone comes as the project’s bulk earthworks programme nears completion. By the end of the project, about three million cubic metres of earth will have been moved across the site, enough to fill Baypark Stadium about 15 times.
“Completing the final major earthworks cut marks the beginning of a new stage of construction,” NZTA said.

Cambridge Rd before the works started (left) and what the road looks like now. Photo / NZ Transport Agency Waka Kotahi
The agency said work is now focused on pavement construction, drainage, utilities and a major asphalt programme that began this month. More than 305,000 native plants have also been planted this season.
Local hapū are gifting ingoa (names) for the bridges to recognise the cultural significance of the area.
The largest bridge on the project is the 367m-long Takitimu Drive Flyover, which narrowly exceeds the 355m Wairoa Awa Bridge.
The flyover also contains the project’s deepest pile at 67m, roughly equivalent to a 20-storey building placed underground.
Meanwhile, the Wairoa Awa Bridge required the most beams, with 80 installed during construction.
The structure has been blessed by local hapū, barriers have been installed and pavement construction is now underway.
Work to remove the temporary construction bridge is expected to begin in late November and take about 10 weeks.
The Minden Gully bridges boast the widest span on the project at 50m and required 129 piles. The structures form part of the new Minden Interchange, which includes on- and off-ramps and a shared walking and cycling path connecting Bethlehem and Tauriko.
At the opposite end of the scale, the 25m-long Smiths Farm Access Bridge is the shortest bridge on the route but is expected to support future growth in western Tauranga by providing access to the planned Smiths Farm development area.
Visible progress is continuing throughout the corridor, including at Fifteenth Ave, where a large retaining wall is nearing completion and crews are carrying out drainage, pavement and approach works around the new Takitimu North Link connection.
Road-widening, drainage and street-lighting works are also underway near the Fifteenth Ave bridge towards Tauriko, with temporary traffic management remaining in place on State Highway 2 until works are complete and Edgecumbe Rd can reopen.

The 15th Ave retaining wall and bridge, pictured in October. Photo / NZ Transport Agency Waka Kotahi
Further west, NZTA said construction has dramatically reshaped the Cambridge Rd corridor between Bethlehem and Tauriko. The emerging expressway is now visible extending through Smiths Farm towards the SH29 and Takitimu Drive Toll Rd connection.
Along SH29, Tauriko Enabling Works continue, with new traffic signals and streetlights installed at the Te Ara Hoia Drive and Cambridge Rd intersections. The signals are expected to become operational in early to mid-2027.
Looking ahead, NZTA said the focus is now on connecting the various elements of the network and completing the new road.
“Proposed speed limits for the new route are expected to be released in the new year as construction continues towards completion,” the agency said.
Investigations for Takitimu North Link Stage 2 are also continuing in the Te Puna area, including environmental monitoring around waterways and wetlands near Munro Rd, Gill Lane and Ainsworth Rd. Night-time monitoring work is being undertaken through November and December, with further investigations planned for summer 2027.