A section of McLaren Falls Rd will be closed during the day for around five months.
During this time, road renewal and stormwater improvement works will be taking place, a Western Bay of Plenty District Council statement said.
The closure affects a 1km stretch of road between Walter Henry Drive and 377 McLaren Falls Rd and began today.
The road will be closed to traffic from 7am to 5pm, Monday to Friday, with some weekend work also planned when required. Outside those hours, the road will remain open.
Western Bay of Plenty District Council director of transportation Calum McLean said the project was part of the council’s ongoing road maintenance, operations and renewals programme.
“The road is being widened on both sides and the area is too narrow for traffic to pass through safely during working hours, so the road needs to be closed to carry out the work,” McLean said.
“We understand this may cause some inconvenience, and we will make efforts to minimise disruption. Your patience during the work is appreciated.”
Resident access will be maintained from either end of the closure, although through traffic will not be able to pass during working hours. Emergency services will have access at all times.
There will be no changes to school bus routes, with buses able to travel through the work site at normal times. Access will also be maintained at the Walter Henry Drive intersection for school bus drop-offs and pick-ups.
McLaren Falls Park will remain open throughout the project.
The works include widening the road, rebuilding and resurfacing the pavement, installing new kerb and channelling, restoring roadside swales, and replacing stormwater culverts aimed at reducing flooding impacts.