Those planning to travel on State Highway 29 (SH29) between Tauranga and the lower Kaimai Range can expect some roadworks and disruptions from early 2027 as teams take advantage of the sunny weather to push ahead at the big three project sites, says NZTA.
From early January 2027, they will start the big job of connecting SH29 into the new road approaches at the Ōmanawa Rd intersection.
They will first rebuild and strengthen the road edge on the Hamilton-bound side, immediately west of the intersection.
There will be temporary steel barriers to replace the flexible hit-sticks to protect crew working beside traffic.
The crew will be working at night with lane closures and stop/go traffic control on SH29 and Ōmanawa Rd.
Both lanes will remain open during the day, but the road surface will be uneven while the layers are removed and rebuilt, with work expected to take about four weeks.
The main work being to join the existing state highway to the new road is likely to start later in March, with some expected disruption and road closures.
Closer to Tauranga city along the SH29/Takitimu Drive Toll Road (TDTR), there will be regular night closures from early January through to late April.
Takitimu North Link crews will continue work on building a major interchange connecting the new expressway to SH29/TDTR and rebuild and resurface SH29/TDTR between Tauriko and Tauranga, as part of maintenance work on this corridor.
- NZTA’s guide to upcoming works
Bay of Plenty
Tauranga and Western Bay of Plenty
SH2 north of Tauranga is a busy route with several worksites, including the Pahoia/Esdaile roundabout, Wairoa River Bridge cycleway repairs and a road rebuild near Woodland Road, north of Katikati. Chipseal sites along the route will be completed in the new year.
Temporary speed limits, lane shifts and stop/go traffic management can cause delays to add up. Please allow extra time, follow signs and crew instructions, and be patient with roadworkers and other road users. We know delays can be frustrating and appreciate your patience.
Work starting next week
- SH2 Tauranga Eastern Link Wairākei Interchange: The Wairākei Interchange on and off ramps will be closed at times overnight to safely remove temporary steel barriers. The Tauranga-bound on-ramp will be closed Thursday 3 December between 8pm and 11pm. The Pāpāmoa-bound off-ramp will be closed early Friday 4 December between 12am and 4am. Traffic will be detoured via Te Okuroa Drive and Tara Road.
- SH29/Redwood Lane: From Sunday 29 November, one night of surfacing is planned near the Redwood Lane roundabout. Stop/go and a 30km/h speed limit will be in place around the roundabout, with Redwood Lane restricted to residents-only.
- SH29 Tauriko: Overnight work starts on Sunday 29 November, between 6pm and 6am, Sunday to Thursday, for 2 and a half weeks. Work will take place on SH29, Cambridge Road and the Whiore Avenue bus link. Expect stop/go as needed on SH29, Cambridge Road and Te Ara Hoia Drive, and a 30km/h reduced speed limit on all approaches to the work sites. Crews will resurface the road, reinstate stormwater trenches, remove temporary safety barriers, mark lines and install traffic signal loops. Cambridge Road daytime work starts Monday 30 November. Expect stop/go and a reduced speed limit from 9am to 3pm, Monday to Friday. Landscaping and construction of the maintenance strip are expected to take 1 week. Guardrail installation starts on Monday 7 December and is expected to take 2 days
- SH2 near Bridge Marina, Tauranga: 1 night of asphalt resurfacing will take place near the Bridge Marina on SH2 on Sunday 6 December. There will be a lane closure and stop/go traffic management between 8pm and 5am.
Work underway
- SH29 Ōmanawa Bridge: There will be night works from Sunday 29 November for 3 weeks. Crews will work at the Ōmanawa Road intersection during the first week, then near the eastern side of the existing bridge for the remaining 2 weeks. Working hours will be between 8pm and 4:30am, Sunday to Thursday with temporary lane shifts and stop/go traffic management in place at times to ensure the work can be done safely. During the day a temporary 50km/h speed limit applies.
- SH29/Redwood Lane: Foundation works for an art installation at the Redwood Lane roundabout continues 7am to 5pm, Monday to Friday. During these hours, temporary traffic management applies on all approaches, with the roundabout reduced to a single lane in each direction, and a reduced speed limit. At the end of each shift, all lanes reopen, with only a shoulder closure remaining and the speed limit back to 70km/h. The work is expected to be completed next week and is weather dependent. Once the foundation is complete, a night shift will be needed to lift the artwork into position. The date is yet to be confirmed.
- SH29 Tauriko Village: The temporary traffic layout remains in place through Tauriko Village while pavement construction continues. Shoulder closures, safety barriers and lane shifts are expected to remain until later in the year. The new left-turn lane from Cambridge Road onto SH29 is now open in its final location. Drainage work continues in the Tauranga-bound lane towards the SH29/SH36 roundabout. The slip lane onto Takitimu Drive Toll Road remains closed from 9am to 3pm, Monday to Friday. During these hours, motorists should use the SH29/SH36 roundabout to access the toll road. The slip lane reopens at 3pm each day, with a wide shoulder closure in place. On the Hamilton-bound side of SH29, a shoulder closure remains from opposite 696 SH29 to the new Whiore Avenue bus link. This allows teams to install streetlight ducting and guardrails, and complete landscaping. The closure is expected to remain until later in the year.
- SH29 Takitimu Drive Toll Road: A reduced 70km/h speed limit remains in place while crews work behind barriers to construct the major interchange for Takitimu North Link Stage 1.
- SH2/Fifteenth Avenue: Crews are completing drainage and building the approaches at the top of Fifteenth Avenue. Pavement work continues at ground level. The lane closure near Edgecumbe Road will remain until late 2026. Road widening, drainage and street lighting work are underway at the bottom of the Fifteenth Avenue bridge towards Tauriko. An extended lane closure, a 50km/h speed limit and a lane diversion remain in place on SH2 between the Eleventh Avenue off-ramp and SH29/Takitimu Drive Toll Road.
- SH2/Pahoia/Esdaile intersection: Construction of a new roundabout is underway and is expected to finish in late 2027. Watch for lane shifts, speed restrictions and intermittent stop/go traffic management, which may cause longer delays.
- SH2 Wairoa River Bridge cycleway: Permanent cycleway repairs have started and are expected to finish by Monday 7 December. Crews work away from the state highway from 6am to 6pm on weekdays. Weather and an additional slip have delayed the opening of the cycleway, this is now expected by Monday 7 December.
- SH2 near Duncan Lane, Ōtamarākau: A road rebuild between Duncan Lane and Ōtamarākau is underway, finishing in mid-December. Work will take place Monday to Friday 6am to 6pm. During work hours, traffic will use one lane under stop/go traffic management. The road will be open to 2-way traffic outside of work hours and at weekends. A temporary 30km/h speed limit will remain in place through the worksite, including when crews are not working. This work continues the rebuild started during the 2025/26 maintenance season.
- SH2 Maunganui Road: A road rebuild between the Golf Road roundabout and Concord Avenue is underway at night between 8pm to 5am and is expected to finish by Thursday 3 December. There are lane closures and detours in place at times.
Work starting soon
- SH2 Takitimu Drive/11th Avenue offramp: Asphalt resurfacing will start soon on the 11th Avenue offramp on SH2 Takitimu Drive, this work will take 3 nights to complete between 8pm and 5am. The ramp will be closed during this time with a detour via Elizabeth Street and Cameron Road. More information to come.
Rotorua
- SH5 South of Rotorua: Road repairs on SH5 south of Rotorua will start next week and continue through to the new year, with crews taking a break over Christmas. Most of this work will take place at night between 7pm and 6am, although there may be the odd day shift. Motorists can expect stop/go traffic management and reduced speed limits while work is underway.
- SH36 Tauranga Direct Road: Construction is underway to replace a culvert at Hauraki Stream, 1km north of the SH36/Hamurana Road intersection. Traffic will shift in early December to the north side and remain one lane, controlled by temporary traffic signals. Lane and shoulder closures and a temporary 30km/h speed limit are in place. Minor delays are expected. Construction will finish in 2027. Oversized vehicles must continue to use SH2, SH33, SH30 and SH5 when travelling between Rotorua and Tauranga.
- SH5 south of Waiotapu: A road rebuild south of Waiotapu is underway and expected to finish mid-December. Work will be carried out during the day, between 8am and 5pm, Monday to Friday. Stop/go traffic management and a reduced speed limit will be in place.
Eastern Bay of Plenty
Work underway
- SH2 Waimana Gorge: A road rebuild south of Tāneatua is underway and is expected to finish in mid-December. Crews work from 7:30am to 6pm. Stop/go traffic management and a reduced speed limit apply around the clock. Expect delays.
- SH2/Ōhiwa Beach Road/Waiotahe Valley Back Road intersections near Ōpōtiki: Traffic is using the new teardrop roundabouts on either side of Waiotahe River Bridge. To turn right from Ōhiwa Beach Road or Waiotahe Valley Back Road, first turn left onto SH2, cross the bridge and use the opposite teardrop roundabout to change direction safely. A temporary 30km/h speed limit and traffic management remain in place while crews finish the work. Surfaces may be uneven. Please slow down, follow signs and allow extra travel time while everyone adjusts to the new layout. Completion is expected in mid-2027.
Work starting soon
- SH2/Wainui Road, Matekerepu Bridge, near Ōpōtiki: Allow extra time when travelling overnight on SH2 between Wainui Road and Ōpōtiki. Matekerepu Bridge reseal works take place on Monday 7 and Tuesday 8 December, from 7pm to 5am each night. Crews will replace part of the asphalt and lay the final bridge surface for a smoother, longer-lasting finish. Work finishes at 5am on Wednesday 9 December. One lane will remain open under stop/go traffic management for most of each night. Traffic in both directions may be stopped up to 4 times each night, for up to 20 minutes each time, while paving machinery moves across the bridge. Emergency vehicles will have access throughout the work.
Waikato
Thames-Coromandel, Hauraki and Matamata-Piako
Coromandel Peninsula: The summer chipseal programme is underway across the Coromandel Peninsula. Warmer weather and higher ground temperatures help the bitumen and sealing chips bond properly, creating a durable road surface.
Chipsealing is planned at various sites across the region between now and April/May 2027. Motorists can expect stop/go traffic management and reduced speed limits while work is underway. Reduced speed limits will remain in place until the new chip has bedded in and road markings have been reinstated.
Work starting next week
- SH25 Whangapoua Road, Coromandel: Crews will be undertaking asphalt resurfacing on SH25 Whangapoua Road just east of Coromandel township, work will take 3 nights to complete starting on Tuesday 1 December between 8pm and 6am. There will be stop/go traffic management through the night and a reduced speed limit in place during the day through the worksite. Delays of 5-10 minutes can be expected.
- SH25 near Hikuai Bridge: A road rebuild will start on Monday 30 November on Tairua Road near Hikuai Bridge on SH25. Work will take around 6 days, with crews working from 7am to 6pm Monday to Friday with completion due on Friday 11 December. Stop/go traffic management and a reduced speed limit will be in place.
- SH2 Waihī: Work starts on Monday 30 November on a right-turn bay into Dean Crescent, which services an industrial area including the Waihī transfer station. There will be shoulder closures, stop/go operations and a speed restriction in place, so short delays can be expected. Access to Dean Crescent businesses and properties will be maintained. Work will be completed before Christmas.
Work underway
- SH2 Mangatarata: SH2 between Ngatea and Mangatarata has closed for 3 weeks for a road rebuild. It is expected to reopen by Monday 7 December. Crews will remain on site the following week for minor finishing work. Residents can access their properties from the relevant side of the closure at the SH2 intersections with SH27 and Pipiroa Road. The worksite between Mahuta Road North and Canal West Road will be fully closed to through traffic, except emergency service vehicles. The detour in both directions uses Pipiroa Road and SH25, reconnecting with SH2 and adding around 12 minutes to journeys. Ngatea township and local businesses remain open and accessible.
- SH27 Horrell Road/Number 4 Road intersections: Safety improvements are underway at the SH27 intersections with Horrell Road and Number 4 Road in Te Puninga. Work includes right-turn bays, safety barriers, a raised median island, and upgrades to drainage, signs and streetlights. Completion is expected by mid-December, weather permitting. Horrell Road, between Manhire Road and SH27, and Number 4 Road, between Number 7 Road and SH27, are closed from 7am to 6pm, Monday to Friday. Both roads reopen outside these hours and on weekends, although some Saturday closures may be needed. Access for residents, emergency services and school buses is maintained. The detour uses Manhire Road, Number 9 Road East, Number 7 Road and Number 2 Road. Detour signs remain in place around the clock; please use the detour to help protect the worksite. SH27 remains open, with stop/go traffic management from 7am to 6pm during work hours. Delays of 5 minutes or less are expected on SH27 and the detour routes.
- SH25 Ramarama Stream: Work is underway to replace the single-lane bridge just north of Whiritoa. Temporary traffic lights currently control vehicles through the site under stop/go. Traffic will be on one lane of the new bridge around early spring 2027 to allow the new road approaches to be constructed in stages and demolition of the old bridge. Completion of the new bridge and approach roads is expected to be early 2028.
- SH25 Tairua: Construction of the new Pepe Stream Bridge continues until late 2027. Vehicles, pedestrians and cyclists can continue to cross the stream, but occasional delays are expected. The project shuts down for the Christmas-New Year holiday period from 18 December, with the crews returning on 11 January. The existing single-lane bridge will continue operating under priority give-way over the holidays, and a traffic management team will be in place over the peak holiday period as in previous years – running from 26 December to 4 January.
- SH27 Ohinekaua Stream Bridge replacement: Work continues to replace the bridge 5km south of Patetonga. Traffic is on a temporary single-lane bridge with a 50km/h speed limit. Expect delays. The diversion bridge is 3.2m wide and cannot accommodate over-dimension vehicles. The new bridge is expected to be completed by the end of this year.
- SH27 Piako River Bridge: Strengthening work continues into December, with a 30km/h speed restriction in place. Single-lane closures and stop/go traffic management may be required.
West Waikato
Work starting soon
- SH3 Ōtorohanga: The Ōtorohanga Christmas parade will take place on Friday 4 December from 6pm through the main street of town on SH3, the road will be closed from 5pm with a detour for all vehicles via Huiputea Drive.
Work underway
- SH3 Te Kuiti to Ōtorohanga: There is intermittent stop/go on State Highway 3 between Te Kuiti and Otorohanga for slip repairs and general maintenance work. Please allow extra time for your journey in this area.
- SH23 Raglan – Greenslade Road: A road rebuild is now underway near Greenslade Road. Crews work from 8:30am to 5pm on weekdays and some Saturdays. Work is expected to be completed by mid-December. Stop/go traffic management and a reduced 30km/h speed limit are in place. Expect delays.
- SH23 west of Whatawhata: Repairs to a slip above the road have started. Stop/go traffic management operates from 7am to 5pm until early December.
- SH31 Kāwhia – Te Rauamoa Road: Enabling work near Te Rauamoa Road is underway and is expected to finish soon. Crews work from 8:30am to 5pm each day, with stop/go traffic management and a reduced speed limit. A full road rebuild is expected to run from late-November to mid-December.
- SH31 near the Kāwhia lookout: Underslip repairs are underway and are expected to finish in early December. Crews work from 6am to 6pm, Monday to Friday, with weekend work as needed. The road is reduced to one lane, with stop/go traffic management and a temporary 30km/h speed limit.
- SH39 Mangati Bridge: A reminder that the temporary single-lane Acrow bridge will close on Monday 30 November, from 10am to 11am and from 12pm to 1pm, while beams for the new bridge are lifted into place. Drive carefully past the site and observe reduced speed limits. The Mangati bridge is being replaced after the old one was damaged beyond repair by flash flooding in February. Traffic will be using the temporary single-lane Acrow bridge until the new bridge opens in early 2027.
- SH3 Awakino Gorge: Work continues on the retaining wall to accommodate the new lane. SH3 will remain open under stop/go traffic management while this work continues. The project remains on track for 2-lane access through the gorge to be restored by mid-December.
Hamilton and Central Waikato
Work underway
- SH1C Riverlea, Hamilton: A temporary speed limit is currently in place in preparation for erosion protection works on the Dreadnought Culvert and associated footpath and retaining wall repairs in that area. Traffic is down to one lane in each direction with a 50km/h temporary speed limit. Expect delays in this area at peak travel times.
- SH1 Waikato Expressway – Cambridge section: Asphalting works on the SH1 Cambridge section of the Waikato Expressway are complete, with permanent line marking to start now the new surface has bedded in. The team will use the SH1 closures from Piarere to the Victoria Road Interchange on Tuesday and Wednesday, 8 and 9 December, to complete some of this line marking south of the Victoria Road Interchange. They will then complete line marking north of Victoria Road Interchange to Tamahere at night from 9pm to 5am using lane drops and a temporary speed limit of 70km/h. Some single overnight ramp closures will still likely be needed at the Victoria Road Interchange (Hautapu) and at the Cambridge Northern Interchange, the Velodrome Cambridge West exit. Any ramp closures will be staged, one at a time, between 8pm and 5am each night. We’ll keep you updated on the dates for these.
- SH1 Waikato Expressway – Karāpiro: As part of early work for the Cambridge to Piarere Expressway extension, SH1 will be closed overnight in both directions between the Victoria Road Interchange (Hautapu) and the Piarere SH1/SH29 intersection. Closures will run from 9pm to 5am on Tuesday 1 December, Wednesday 2 December, Tuesday 8 December and Wednesday 9 December, to relocate Transpower high voltage lines crossing SH1. Southbound traffic from Hamilton/Cambridge towards Tīrau/Piarere will detour via SH26 → SH27 → SH29, rejoining SH1 at the Piarere roundabout. Northbound traffic will use the reverse route. The detour adds approximately 73km and 57 minutes to journeys. Residents and emergency services will be piloted through the worksite from the Cambridge Southern Interchange for southbound travel, and the SH1/Hydro Road intersection for northbound travel.
South Waikato and Taupō
Work starting next week
- Lake Taupō Cycle Challenge: The Lake Taupō Cycle Challenge will see thousands of riders take on the iconic course around Taupō this Saturday 28 November. The state highways remain open but there will be temporary speed limits on SH1, SH32 and SH41. Remember, drivers must leave at least 1.5m gap when passing other road users. If you can’t pass safely, slow down and wait until you can. Expect delays and consider alternative routes.
- SH30 near Bennydale: Enabling works will start on Monday 30 November near Waimiha Road, Bennydale, taking 3 weeks to complete. The work includes vegetation clearance, tree trimming and shoulder widening. In the new year the drainage and a road rebuild will start from Wednesday 13 January 2027. The work will take place between 7pm and 7am Monday to Saturday, stop/go traffic management will operate 24 hours a day.
Work underway
- SH30 near Barryville: Vegetation clearing has started near Barryville Road and will take about 3 weeks to complete, finishing mid-December. Crews work between 7am and 7pm each day, stop/go traffic management is in operation 24 hours a day. From Wednesday 13 January to Friday 19 March, drainage and a road rebuild will take place, crews will be on site between 7am and 7pm Monday to Saturday, stop/go traffic management will be in place 24/7. Delays of up to 10 minutes are to be expected.
- Arapuni Dam: Arapuni Road across Arapuni Dam is closed until 2028 while Mercury carries out major repairs. The temporary detour via Powerhouse Road is for light vehicles only, including cars, motorcycles, school buses, emergency services and rigid trucks up to 8 metres. General through traffic, heavy freight/commercial vehicles and long-distance traffic should use SH1/SH21 and SH3.
- SH5 South Waikato: Work is nearing completion to widen SH5 near Waimakariri Road and install wide centrelines. The work covers 1.2km, extending the existing wide centrelines from Whites Road to the new SH28–Harwoods Road roundabout. There is stop/go in place during sealing work and minor delays are expected.
- SH5 east of Taupō: Crews have resumed the road rebuild, working from 6am to 6pm, Monday to Friday, with occasional Saturday work. Work is due to be wrapped up next week. During work hours, 2-way stop/go traffic management will be in place. Allow for delays of up to 10 minutes. A temporary 30km/h speed limit applies both during and outside work hours.
- SH5 south of Rangitaiki School: Enabling work for a road rebuild has begun south of Rangitaiki School finishing on Friday 4 December. A temporary speed limit will be in place, with delays of up to 10 minutes during work hours. The road rebuild will start in early January 2027 and take 5 weeks. Crews will work from 6am to 6pm, Monday to Friday.
- SH5 Tarawera (Napier/Taupō road): A road rebuild is underway until Wednesday 16 December, between 7am and 5pm, Monday to Friday. Stop/go traffic management will be in place during work hours, with delays of up to 10 minutes. Outside of work hours, a 30km/h temporary speed limit will be in place.
North Waikato
Work starting next week
- SH1 Pōkeno to Pioneer Road: There will be a full southbound closure on Sunday 29 November between 9pm and 5am. Traffic will still be able to travel south using one of the northbound lanes.
- SH1 Pioneer Road to Island Block Road: There will be a full southbound closure on Monday 30 November between 9pm and 5am. Traffic will still be able to travel south using one of the northbound lanes.
- SH1 Nikau Road to Pōkeno: There will be a full southbound closure on Wednesday 2 December between 9pm and 5am. SH1 southbound to SH2 eastbound link and SH2 westbound to SH1 link will also be closed. Traffic will still be able to travel south using one of the northbound lanes. SH2 contraflow to O’Leary Road may also be in place as part of this closure.
- SH2 Steen Road to SH25 Roundabout: Stop/go traffic management will be in place for maintenance on Wednesday 2 December between 9pm and 5am.
- SH1 Huntly and Taupiri: Waikato District Council will start work on the former SH1 late November. Planned summer work is listed below. For more information: here Surfacing the northbound slip lane exiting Huntly’s main street
Surfacing the intersection of Tainui Bridge Road and Great South Road traffic lights
Repairs in Taupiri, extending from the northern side of Mangawara Bridge, through the 2 roundabouts and finishing just east of the Orini Road roundabout
Replacement of approximately 4km of kerb, channel and footpath
Streetlight renewals across most of the section.
Work underway
- SH1 Waikato Expressway Ngāruawāhia: Road surface repairs have started taking approximately 2 weeks to complete, finishing early December, crews are working day and night to finish as quickly as possible. Traffic will be moved to one side of the expressway, with one lane each way to minimise delays for the duration of the work. Temporary 50km/h and 70km/h speed limits will apply 24/7 in work areas. Repairs cover 4 sites totalling less than 1km where the surface does not meet the required standard. Allow extra travel time, use alternative routes where possible, and follow temporary signs and speed limits through the worksite.
Tairāwhiti
- SH35 Pōtaka to Tikitiki: The work programme includes repairs to overslips and dropouts, drainage improvements, road widening and culvert work. Traffic management will be in place at worksites. Allow extra travel time and follow all signs and instructions. Work is expected to finish by Christmas.