Road works continue on SH2 corridor

State Highway 2 between Bethlehem and Te Puna. Photo: SunLive.

NZTA Waka Kotahi are asking motorists travelling on State Highway 2 in the Waihī to Tauranga corridor to be mindful and aware of the planned road works programme for the week starting March 18, 2024

"While we aim to do this work with as little disruption as possible, we know that roadworks can be inconvenient. Thanks for your patience while we do these important works," says an NZTA spokeserson.

"Please drive carefully through work sites and stick to the temporary speed limits. Our programme is weather dependent, so may be postponed to the next suitable day/night."

Well maintained roads are an important part of keeping people safe.

Intended programme for March 18 to 25

Location

Type of work

Schedule

Maintenance / remaining reseal sites

There are no reseal sites programmed for this week.

Remaining sites to be completed from w/c 26 March are listed below.

  • McMillan Road
  • Aongatete Road
  • Pahoia / Esdaile Roads
  • Lund Road to Forta Leza
  • Highfields Drive, Katikati
  • Challenge, Ōmokoroa
  • Woodland Road
  • Old Fire Station, Katikati

Nightworks under stop/go. Temporary speed limits on the following day with loose chip.

Estimated completion of reseal programme early April.

Athenree Gorge 

 

As part of the safety improvements project between Waihī and Ōmokoroa, 3.8km of flexible median barrier is being installed north of Katikati, through the Athenree Gorge. Widening work has previously taken place at this location, and installation of median barrier has been coordinated with the reseals programme on SH2 this summer. Contra flow in place with speed restrictions.

In progress, estimated completion April 2024

Kauri Point Road to Stokes Road 

 

Service relocations underway. Contraflow and shoulder closures in place with speed restrictions.

In progress

SH2/Sharp Road Intersection 

 

Roundabout construction underway with significant activities. Night works stop/go for concrete and barrier works. There will also be daytime intermittent stop/go traffic management in place which may cause longer delays, but typically expect minor delays of one to two minutes.

Ongoing to mid-2024

Apata Curves 

 

Road widening works underway, these are enabling works for roundabout construction. Contraflow in place with speed restrictions. There will be intermittent stop/go traffic management in place which may cause longer delays, but typically expect minor delays.

Enabling works for roundabout site estimated completion 2025

SH2/Ōmokoroa Road

Shoulder closures in place with speed reduction for early works.

In progress

SH2 Te Puna / Loop Road, Ainsworth Road

Powerline removal, and underground drilling for upgrades will take place between Loop Road and Ainsworth Road, at times both lanes will be held for 2 minutes at a stop/stop while this work is done. Delays are to be expected.

Saturday 16 March

SH2/Te Mete Road, Te Puna

 

Haul road set up to support summer earthworks season for construction of Takitimu North Link, shoulder closure, 60km/h temporary speed limit.

Ongoing

SH2/Fifteenth Ave

Early works underway at SH2/Fifteenth Ave where an on-ramp bridge connection will be built as part of the Takitimu North Link project. Tree felling will take place on with a shoulder closure in place from the Cameron Road intersection onto SH2.

Thursday 21 to Saturday 23 March (7.30am – 6pm)

 

You may also like....

0 comments

Leave a Comment


You must be logged in to make a comment.