The $10 million works currently taking place along Domain Road in Papamoa are progressing satisfactorily says Tauranga City Council manager of transportation Martin Parkes.
The project is currently underway on stage one and two of the works with the only major setbacks being wet weather, which delayed things for a short time.
He says stage two is set to be completed by mid-2020, with stage three on hold pending assessments of development opportunities of adjacent rural land.
The main purpose for these works is to make it safer and easier for people to walk, bike and catch the bus along Domain Road.
The works are spanning over the course of three years and will resurfacing the length of the road to better cope with the numbers of vehicles, along with new landscaping.
Domain Road, Papamoa timeline:
Stage one works between Papamoa Beach Road and Gravatt Road are continuing.
Stage two works are underway between Gravatt Road and The Gardens Drive.
Stage three is currently on hold, but including road reconstruction, including a 2.5m wide shared path on both sides, and completion of landscaping and tree planting.
For more information about the Domain Road safety upgrades, click here: