Work on the Southern Pipeline Harbour Crossing is entering its final stages, with the last phase of reaming now underway.
The reaming work has involved gradually widening the hole beneath the harbour with increasingly bigger reamers. Widening with the 1.4m diameter reamer is now just over halfway complete.
The contractor has faced a number of challenges with work on the project, and initially expected to be in this phase of work about one month ago.
The drilling phase of the project was completed successfully in July – hitting a 750mm diameter target at Memorial Park from a distance of 1.6km and maximum depth of 35m under the harbour from the Matapihi side.
Once the drilling work was completed, the first phase of reaming work began. As the first reamer moved through under the harbour it encountered harder than expected material.
The reaming work progressed slower than expected and specialist machinery was required.
In addition, the reamer encountered an obstruction as it moved through the hole from Memorial Park towards Matapihi.
The obstruction has been removed and identified as a piece of totara wood that is approximately 51,000 years old, which is now in the care of the Tauranga Museum.
'We've encountered a number of interesting challenges on this project, mostly due to the difficult working environment under the harbour. The contractor has experienced difficulties in reaming past the harder materials and obstructions such as the piece of timber,” says Tauranga City Council Project Manager for the Southern Pipeline Steve Wiggill.
"Specialist experts were brought in and additional equipment used, and this together with modifications to the machinery has enabled these challenges to be successfully overcome. Unfortunately, this has had an effect on the overall project timing, and we now expect a small amount of work will need to take place in January.”
Steve says there is no forecast change to the overall $99m Southern Pipeline project budget as a result of these challenges.
Once the reaming work is completed, a short period of between three-to-seven-days of 24-hour work is required to pull the pipes through from Memorial Park to Matapihi.
This will be the last phase of construction work, and is still expected to be completed before the end of the year.
Once the pipes are pulled through under the harbour, there are two other smaller phases of work that will need to be finished before the Southern Pipeline project can be completed and commissioned.
Steve says pipes also need to be laid at both ends of the Harbour Crossing, to connect it back to the Memorial Park pump station, and up Matapihi Road to the previously constructed section of the Southern Pipeline that connects to the Te Maunga Treatment Plant.
Both sites will then be cleared of all equipment and reinstated back to their original condition.
The temporary reclamation at Matapihi will be removed. It is expected that this part of the work may extend into January 2018. No work will take place over the Christmas and New Year period.



6 comments
Wate of money on waste
Posted on 28-10-2017 14:42 | By MISS ADVENTURE
The huge sums involved are simply creating more and more debt for ratepayers with little or nothing to show for it exept the debt.
Museum
Posted on 28-10-2017 14:48 | By Minib
The chunk of wood is now in the possession of the Tauranga Museum, where is this place? I would like to see this 51,000 year old piece of timber. I bet no one can show me where this Museum is.
Slips
Posted on 28-10-2017 15:15 | By overit
I hope its all secure because there are a lot of slips along the waters edge along there-I saw them from my friends waterfront home at Maungatapu.
Not real reasons
Posted on 29-10-2017 12:03 | By MISS ADVENTURE
Reports from the contractors corner are that bentonite has leaked into harbour waters. No one has bothered to report that! Also, the equipment would not notice a tree when drilling as they are designed and made to drill through rock, so unless the tree is petrified and therefore is rock and also therefore in rock even then it would be very difficult to notice any issue arising from any of that. The leakage of bentonite into the harbour more likely provides more insight to what has happened. Likely the drill hole has collasped at least partly so likely snaring the drill equipment and so cuasing delay and the need of new gear. The poor old ratepayer will get slugged for all of this regardless.
Does your s*** not stink?
Posted on 29-10-2017 13:57 | By Calm down
Because if it doesn't then I could totally see why you'd be angry about the council spending money on waste water treatment. But unfortunately for most of us rate payers our s*** does stink so we need a sewer system to take it away for us.
Makes sense to me Miss Adventure
Posted on 29-10-2017 14:03 | By Centurion
I work with rock, gemstones, petrified wood etc as a hobby. A rock cutting drill of the size used under the harbour wouldn't even notice a piece of wood in its way.
Leave a Comment
You must be logged in to make a comment.