Tauranga’s Memorial Pool redevelopment could be put on ice for at least three years.

Tauranga City Council’s elected members voted to consult the public on deferring the project as part of the city’s next Long-term Plan (LTP).

The proposal would pause work on a replacement aquatic centre while the council developed a citywide aquatic network plan. This left the future of the closed Memorial Pool complex unresolved.

The deferral was one of several cost-saving measures debated at a November 10 council meeting.

Elected members looked for ways to reduce capital spending by about $200 million to prepare for the Government’s proposed rates cap.

The Local Government (Rates Capping) Amendment Bill passed its first reading in September. It would require councils to cap annual rates increases at 4% per capita.

Councils would have to consider the cap in their long-term plans from July, before it becomes mandatory in 2029.

The city council set an average 7.2% increase this year, following the 9.9% increase in 2025.

Elected members spent hours debating whether certain key projects should be deferred or rescoped to meet rates targets.

The projects discussed included the Connecting Mount Maunganui transport project, Domain Rd upgrade stage two and the Mount Sports Squash Club building development, and halving the Mauao remediation budget.

The proposed changes fell about $6m short of the $200m target and had potential consequences such as delayed outcomes, reduced service levels and extending infrastructure and facility deficits.

An architect's render of the Memorial Park upgrades. Image / Tauranga City Council
An architect's render of the Memorial Park upgrades. Image / Tauranga City Council

During the commissioners’ tenure, the council planned a $124m project to build a Memorial Park Aquatic Centre with indoor and outdoor pools, three hydroslides and a splash pad.

The project was later scaled back to an $81m concept focused on core services including lane swimming, sports, learn-to-swim programmes, hydrotherapy and recreational use.

The council approved $4m of funding in May to decommission and demolish the existing pool, and progress the concept to detailed design and consenting.

This work would pause until the council made a final decision as part of the Long-term Plan process.

The council has described the pool as in an “end-of-life” condition, with leaks and an “ageing” heating system.

Tauranga Memorial Pool. Photo / Kelly O'Hara
Tauranga Memorial Pool. Photo / Kelly O'Hara

It closed permanently in April after operating at 20% visitation capacity during summer.

Bay Venues community facilities general manager Paul Dunphy said the council was updating the aquatic network plan to look at Tauranga as a whole and determine how best to meet community needs.

This covered lane swimming, learn-to-swim, hydrotherapy and recreational swimming.

“The council has included $10m over the first three years of the draft Long-term Plan to investigate and progress options across the networks, and $3.8m for improvement at Ōtūmoetai Pool.”

He said decisions on the future of the Memorial Park building and pools needed to be considered alongside this work and the future role of the Memorial Park site.

He said the LTP would confirm the next steps for the existing complex, including its retention or removal, and the timing of any works.

Jan Iles petitioned against demolishing the Memorial Pool, which was built after World War II as a memorial to those who died serving.

She said the proposed aquatic centre project had raised many community concerns. The growing debt burden on ratepayers was one of the most significant.

 Jan lles started a petition asking Tauranga City Council to defer making a final decision about whether to demolish Tauranga War Memorial Pool until after public consultation. Photo / Kelly O'Hara
Jan lles started a petition asking Tauranga City Council to defer making a final decision about whether to demolish Tauranga War Memorial Pool until after public consultation. Photo / Kelly O'Hara

Iles told Local Democracy Reporting it was good the council had shown willingness to investigate a citywide aquatic network and work with community representatives.

“The decision process still has a long way to go.

“The council are going to work with us. We consider that to be very positive.”

She said a Heritage NZ nomination had been lodged for the pool. Tauranga RSA provided support letters.

“No war memorial pool in New Zealand has ever been demolished.”

In an email to Iles, interim council chief executive Gareth Green said the council had agreed in principle to do an Aquatics Network Plan and put a placeholder amount in the budget for upgrade works across the network.

Another vocal local on pool issues, Suzie Edmonds, said she was encouraged by the council’s proposal to take a broader look at aquatic facilities across Tauranga rather than focusing on a single aquatic centre.

Project STOP – Save the Ōtūmoetai Pool founder Suzie Edmonds speaking at a Tauranga City Council meeting on May 27, 2025. Photo / David Hall
Project STOP – Save the Ōtūmoetai Pool founder Suzie Edmonds speaking at a Tauranga City Council meeting on May 27, 2025. Photo / David Hall

She said reviewing the wider pool network was “very sensible” and supported spreading learn-to-swim opportunities across Tauranga.

Edmonds said local pools remained important for families and communities.

Council major projects director Jane Small said staff were working with Bay Venues on the scope and timing of the proposed network plan.

“The council is taking time to reassess existing aquatic facilities and future needs for Tauranga before investing ratepayers’ money.”

The LTP will be consulted on early next year.

Ayla Yeoman is a Local Democracy Reporting journalist based in Tauranga. She holds a Bachelor of Arts majoring in communications, politics and international relations from the University of Auckland, and has been a journalist since 2023.

LDR is local body journalism co-funded by RNZ and NZ On Air.

0 comments

Leave a Comment


You must be logged in to make a comment.