A decade-long wait for a replacement bridge and intersection at a flood-prone Coromandel site has led to a 440% cost increase from $12 million to $65m in a stark illustration of runaway construction costs for delayed infrastructure.
The public will pick up more than $50m in extra costs, despite a minister allocating funds to the job in 2016, as the long lead-in time coincided with Covid-driven inflation.
The replacement Kirikiri Stream Bridge and nearby state highway intersection construction is part of work on multiple sites across the peninsula’s State Highway 26 under resilience improvements.
The NZ Transport Agency Waka Kotahi was now “refining the scope, including reviewing the previously applied scope to identify the best value-for-money solution within the available funding”, it told Local Democracy Reporting.
Budget 26 allocated $85m for the network’s improvements, with $65m of that going on a new Kirikiri Stream Bridge on SH26.
The bridge and parts of the highway will be raised by three to four metres to provide clearance for floodwater and debris, with the nearby SH26/SH25A intersection also to be rebuilt, NZTA regional manager, infrastructure development and delivery Roger Brady said.

The network acts as a key corridor for the Coromandel. Photo / Christel Yardley, Waikato Times
Ten years ago, Transport Minister Simon Bridges announced funding of $12m for the project, which included the replacement bridge, realignment of the highway and an upgraded intersection.
Asked if the subsequent cost blowout was an indication that the project should have been completed sooner, Brady said it had been in development for several years, and therefore “current funding allocation is not directly comparable with earlier estimates”.
“Those estimates pre-date Covid-19 and the significant rise in construction costs since then, particularly for labour, steel and other materials.”
The project was market-tested again in 2023, he said, when a construction tender price was about $35m, with total funding requirements clocking in at $47m.
“The $65m included in Budget 2026 reflects that market-tested position, with contingency and escalation applied for project risk and the time elapsed since then.”
Former Thames-Coromandel Mayor Len Salt has been vocal on the issue, quoting the adage that “it’ll never be cheaper than it is today”.

Former Thames-Coromandel Mayor Len Salt says the job should have been completed earlier. Photo / Christel Yardley, Waikato Times
He described the cost jump as “quite an extraordinary blowout”, adding that it raised serious questions as it affected the budget available for other Waikato road projects.
“What I’d be asking them [NZTA] is ‘What level of confidence do you have that you can get the job done for $65m without costs over and above that figure?’”
The remaining $20m will see work progressed at Manaia River and Owera bridges between March and July 2027, subject to detailed design being completed.
A further four locations have been identified at Whenuakite, Waikawau, Te Kouma Hill and Whangapoua Hill, with up to five more sites currently being prioritised. Work across these sites will be staged over the next four years.
Thames-Coromandel Mayor Peter Revell previously said he was “absolutely delighted” at the funding’s announcement.

Thames-Coromandel Mayor Peter Revell has welcomed the latest funding commitment.
“The resilience of the network is a concern to everybody on the peninsula partly because communities get cut off ... but also economically for tourists to have the confidence when they come to the peninsula they can get on and off and they’re not going to be killed.”
Further long-term Crown funding will see work delivered on nine sites between March and July next year. These include underslip and rockfall protection work on SH25 Thames Coast Road between Ruamahunga and Tapu, and near Whakatete and Kereta, as well as underslip treatment on SH2 in the Karangahake Gorge near Waikino.

The Kirikiri Stream Bridge and parts of the highway will be raised by three to four metres to provide clearance for floodwater and debris, with the nearby SH26/SH25A intersection also to be rebuilt. Photo / Christel Yardley, Waikato Times
“The SH26 Kirikiri Stream Bridge replacement will help reduce the risk of future disruption on a critical transport route for local communities, businesses and visitors,” Brady said.
“While these improvements cannot remove every risk or prevent all future disruption, they will reduce the risk at priority locations and help make state highway connections around the Coromandel better able to withstand severe weather.”
- LDR is local body journalism co-funded by RNZ and NZ On Air.