Mayor backs urgent repairs to mouldy council HQ

Thames-Coromandel District Council is facing a hefty bill to remedy broken council admin buildings. Photo/ Mark Jephson, Waikato Times (single use)

Three months after black mould forced the closure of parts of Thames-Coromandel District Council’s administration building, the council has been forced to act.

On Tuesday, councillors voted for an investigation and works budget of up to $500,000 to address not only the toxic workplace, but multiple compliance issues.

The Thames building carries an earthquake-prone label, holding a rating below 34% of the New Building Standard, and that is “expected to form a major component of any future refurbishment”, the council’s corporate services group manager, Oonagh Hopkins, said.

The building’s fire alarm systems, evacuation systems and fire-related construction create “life safety and statutory compliance risk”, the council agenda read, with multiple spaces also lacking fresh air supply.

Damage is even noticeable in council chambers, as councillor Flemming Rasmussen pointed from his seat saying, “the hole in the sarking is getting bigger and bigger”.

 Thames Coromandel District Council councillor Flemming Rasmussen pointed out a glaring fix needed in council chambers. Photo / Supplied
Thames Coromandel District Council councillor Flemming Rasmussen pointed out a glaring fix needed in council chambers. Photo / Supplied

Hopkins said the recommendation made to the council was to adopt a five-workstream approach, in which staff would come back “in August at the latest” with specific building upgrade options to be implemented.

About $50,000-$60,000 of the total $500,000 would be immediately attributed to fix “known building defects, reopen areas currently closed to staff and improve working conditions across both the TAB and County building”, Hopkins added, noting most of the work has already been quoted.

The council’s county building and the Whangamatā Service Centre were also included, as both contain active mould. Investigations into the main admin building have been running since 2017.

A “high-level cost” concept design was produced in 2025 by staff to fully refurbish the building, according to the agenda, totalling $14.1-$16 million. It remains subject to further review and refinement.

 Thames-Coromandel District Council mayor Peter Revell is all smiles now his admin building is getting fixed. Photo / Supplied
Thames-Coromandel District Council mayor Peter Revell is all smiles now his admin building is getting fixed. Photo / Supplied

Mayor Peter Revell said the work is “absolutely needed”, adding that he now hopes to see “rapid implementation” of initial works now that staff have the funding.

Revell couldn’t comment on why no concrete action was taken before the black mould arose, saying it was before his mayoral tenure.

He re-emphasised how the discovery of black mould three months ago, with the non-compliance, was the main driver. He added that the process of earthquake-proofing the building “began in the previous triennium”.

Staff factoring in amalgamation and the council’s three short-listed options is critical, as by the time their proposal is presented, the council will have “a much clearer idea” of which way the district will go, Revell said.

“Depending on which of those three options we adopt, we could end up potentially with three quite separate requirements for those buildings and teams.”

LDR is local body journalism co-funded by RNZ and NZ On Air.

2 comments

The Master

Posted on 26-06-2026 17:16 | By Ian Stevenson

Hmmmm, Councils building buildings, sounds like a disaster before it starts?

Councils seem to have a genuine and ingrained ability to attract mold... this directly relates to the massive quantities of hot air that extolls 24/7 in and around the place.

Perhaps a concrete only box type construction, with an automated flush system to remove all the nasties at least daily would help a lot.


Same excuse as Tauranga City Council

Posted on 30-06-2026 18:02 | By Rockbit

Here we go again, how to manipulate the rate payers. Exactly the same excuse was used by the Tauranga City Council to have an ultra luxury council office build at a cost of $92 million paid for by the rate payers for a 15yr lease. They don’t even own the building, it will be an eternal lease funded conveniently funded by the rate payer and owned by the privately owned Property Income Fund. So here you go, the rate payers fattening the wallets of a select group shareholders, laughing whole the way to the bank. Thank you Mahē Drysdale , what an excellent job you did for the ratepayers to flees them from their hard earned money !!


Leave a Comment


You must be logged in to make a comment.